AgrolaAutarcoAxpoBEE EnergyCompanion EnergyDynamic Energy TradingDexterDNO Relay ControlEdmijEnergy Flexibility Solutions (EFS)EliaEnervalisEngiePlan-ahead APIEPEX Spot SolarEuropean CommoditiesFlowerFrank EnergieFuseboxGreenchoiceHallostroomImbyJoulenKratTradeNew integrationsNext EnergyOpinumParagraph 14a IntegrationPleeviRepoweredScholtTrevionVGT EnergyYuso - Battery ControlYuso - Solar Curtailment
SpecificationsStatus LEDsControl response timeVideo tutorialsCertificatesLicenseSafety, maintenance and legal notices
External Signals
Engie logo

Setting up Engie

The manual describes the steps to set up Engie External Control on the SmartgridOne Controller.

When setting up this integration, permission is granted to Engie to control the necessary devices.

Supported Devices

Device TypeVariantsSupported
Solar InvertersAll✅
Storage Devices
EV Chargers❌

Supported Countries

CountrySupported
Belgium✅
Netherlands❌

Prerequisites

1. Add the batteries

Login to the commissioning interface and make sure the devices are added to the SmartgridOne Controller.

2. Check the grid power limits

In the settings, the grid power limits should be set correctly. Click Settings and check the highlighted setting in the image. If necessary, adjust the settings.

Add 'Engie - External Control'

Image 1
Image 1

In the next page, you have the option to include/exclude devices for remote control. Ensure to mark all checkboxes of devices you'd like to include.

Note

When using multiple batteries, they are aggregated into one (virtual) asset for Engie.

Image 1

'Engie' is now set up on the SmartgridOne Controller.